• $4 million
    Invested

The project involves the installation of quality stone paving throughout and the installation of landscaping to position Moonta Street as a comfortable green promenade and a premium precinct for evening activity.

This project will enhance and strengthen Chinatown by improving the amenity, connectivity and activation of the precinct.

Total investment: estimated at $4 million ($2 million in state government grants, council also received an additional $500,000 through the Planning and Development Fund in 2019/20 as part of the Chinatown Redevelopment election commitment). This involves artistic lighting and public realm improvements along Moonta Street

Project start:
July 2020
Expected completion:
December 2021
Current status:
Planning